Earlier this month, @Epping Gruppe successfully completed a 1,051 m long DN2400 microtunneling drive through the urban area of Zurich — an impressive feat of engineering and collaboration.
Key project facts & challenges:
- Dimensions: ID 2400 / OD 3000 mm
- Complex 3D alignment: multiple horizontal and vertical curves (radii up to R = 250 m)
- Crossings: several streets, railway tracks and buildings
- Ground conditions: highly variable throughout the alignment
- Smart optimization: use of the Hydraulic Joint allowed for three different jacking pipe lengths to maximize performance
- Digital integration: MSS equipped with the BIM Package for visualizing existing (underground) structures and exporting project data in .IFC format
- Congratulations to everyone involved on this milestone achievement — and Glück auf! for the upcoming second drive!
@ewz
@Rothpletz, Lienhard + Cie AG | Bauingenieure & Bauunternehmung
@Locher Ingenieure
@Implenia